Sunday, April 17, 2011

Ready for Cabinets

I didn't think there was any way they'd have tile ready for when the cabinets are delivered on Tuesday.  But when we were there today we discovered that a large part of it is ready.

The kitchen is finished.

I'm very pleased with the tile selection.

...and I'm equally pleased with the grout. I think it's just the right shade of darkness so it won't get stained. 

The master bath and laundry room are also tiled and grouted.
Well, not the entire master bath.  When they roughed in the plumbing, the pipes for my tub were put in the wrong place so someone has to come jackhammer the floor up in order to move the pipes back a couple of feet.  I assume that will happen soon so they can go ahead and finish tiling this area.

But, I could be wrong.

So, it looks like the tile will be ready for the arrival of the cabinets this Tuesday.  They should be able to set the kitchen and master bath cabinets where they belong.  Hopefully tomorrow they can finish up the powder bath, mother-in-law bath & upstairs bath.  All of that tile is pretty large, as well, so it should go quickly.